Exterior supports, interior work

Interior work continues on framing, planking, and ceiling. As the framing and planking is removed, the vessel weight will need to be supported. Exterior supports are being installed to shore up the ‘tween decks areas. More exterior scaffolding will be installed in January, and a shelter will be constructed over the deck to cover topside work areas and allow visitor access. Stair tower assembly has begun and is estimated to take 3 weeks to complete. The three- flight, 30-foot structure will provide deck access via an aluminum gangway.